The $67.5 Million Morrissey Boulevard Deal Is Now a Land Court Fight. The Landowner Says the Developer Simply Ran Out of Time.
POB Capital asks a judge to dismiss Copper Mill's suit over the former WLVI parcel, where the city approved 754 apartments, and to lift a notice warning buyers of the litigation. A hearing is set for Nov. 16.

BOSTON — The Chicago company that owns the former WLVI television station site on Morrissey Boulevard in Dorchester has asked a Land Court judge to throw out a Boston developer's lawsuit over a collapsed plan to build two 18-story apartment towers there, arguing that the developer failed to secure financing before its purchase agreement expired.
In a motion to dismiss filed in Land Court, POB Capital denies Copper Mill's allegation that it tried to back out of the deal after realizing the 2.2-acre parcel was worth far more than the $67.5 million price once the Boston Planning Department approved the 754-apartment project, Universal Hub reported, quoting the filing. The approval came in August 2025.
What the landowner says. "Plaintiffs falsely blame Defendants for the failed closing," the motion states, according to Universal Hub. "They claim that Defendants obstructed fundraising, pursued a competing transaction, and induced Copper Mill into the venture while secretly intending to defeat the purchase. The written agreements and contemporaneous record do not support those allegations."
The filing says the parties jointly pursued financing and that POB consented to Copper Mill's exercise of a contractual extension option. It argues that Copper Mill "never alleges that it could perform the purchase that it now seeks to revive" and that it waited three and a half months after the agreement terminated, after proposing "an entirely different transaction on entirely different terms," before suing. The purchase-and-sale agreement expired on June 30, according to the filing as described by Universal Hub.
What the developer wants. In the Land Court case, Copper Mill is asking a judge to order POB to accept the original $67.5 million price with 12 additional months for Copper Mill to line up funding, Universal Hub reported. In a separate suit in Suffolk Superior Court, Copper Mill seeks damages for what it alleges was fraud and conspiracy by POB after the land's value rose. POB has not yet answered that suit. Copper Mill's claims are allegations that have not been decided by a court.
The lis pendens. Judge Sarah Turano-Flores earlier granted Copper Mill a lis pendens, a notice recorded with the Registry of Deeds warning prospective buyers or investors that the parcel is the subject of litigation. POB is asking the judge to rescind it. Such notices can make it difficult for an owner to sell or refinance property while a case is pending.
Next step. Turano-Flores has scheduled a hearing on POB's motion for 2 p.m. on Nov. 16, according to Universal Hub, which linked the complete motion.
Why it matters. The approved project would add 754 apartments on a single parcel along one of Dorchester's main corridors at a time when the city is struggling to get permitted housing built. On Monday, the Wu administration proposed changes to Boston's affordable-housing rules intended to help stalled projects move forward, saying high interest rates and construction costs have stopped many developments after approval. The Morrissey Boulevard dispute shows a different way an approved project can stall: a fight between partners over who is to blame for a deal that did not close.
What remains unresolved. Neither the court record described by Universal Hub nor public statements show whether any other buyer has approached POB, what the parcel's current valuation is, or whether the approved project could proceed under a different developer.