The FTA Advanced the Green Line's $2 Billion Ask Into Engineering. New Grant Rules Could Still Knock It Out.

The T is already spending local money on Type 10 trains and station work. A proposed federal scoring bonus for corridors with higher marriage and birth rates would not be grandfathered, and General Manager Phil Eng warned the project could fall out of the pipeline.

By Boston Uncut ·

Photo: 4300streetcar / Wikimedia Commons, CC BY 4.0 (source)

The Federal Transit Administration last week allowed the MBTA's Green Line Core Capacity program to enter the engineering phase, the last planning step before a full funding grant agreement. In the same stretch of days, the T was warning that a proposed rewrite of the rules for those grants — including a bonus for corridors with higher marriage and birth rates, and a bar on grandfathering projects already in line — could still push the roughly $4 billion project out of the running for about $2 billion in federal money.

Connor Torossian, the FTA's associate administrator for communications and government affairs, said in a statement quoted by Streetsblog Massachusetts that "by advancing the Green Line's modernization into the Engineering phase, we are backing a smart, practical upgrade to a historic corridor that moves nearly 95,000 people every day." Under current rules, the FTA still cannot approve the grant and send the money until the president includes the project in his executive budget. In the past 22 months, Streetsblog reported, the administration has approved only one Capital Investment Grants agreement, a $149 million grant for bus lanes on Vermont Avenue in Los Angeles.

The T approved an $810 million contract in 2022 for new, longer Type 10 Green Line cars. Those trains will not fit some existing tracks and stations, so the agency has planned a broader suite of work: new tracks, signals and power, station renovations, and yard and maintenance-facility changes. The FTA invited the T to apply for a grant covering half the cost in 2022. The agency's latest project profile, cited by Mass Daily News, lists a federal request of about $2.04 billion. The T had hoped for final approval by April 2027, when the first Type 10 cars are scheduled to enter service.

A CIG project starts in project development, which the T began in 2022. The agency finished the required environmental work, local financing plan and early design in early 2025, then waited about 15 months for the FTA to clear it for engineering. Work in those phases is done at the transit agency's own risk, though the costs count toward the required local match. The T's most recent capital plan budgeted $891 million in Green Line core-capacity spending over five years, including $285 million for a dedicated transitway and new stations for the E branch on Huntington and South Huntington Avenue in Mission Hill; $200 million for B branch stations and tracks on Commonwealth Avenue; a $45 million test track on the D branch in Newton; $33 million to adjust overhead wires; $34 million for D branch electrical upgrades, including a new traction power substation; work on the central tunnel; and $297 million at storage yards and maintenance facilities.

The new uncertainty is in the FTA's proposed rewrite of CIG policy. The proposal would raise a large project's federal share by up to 10 percentage points if the corridor's birth or marriage rates are above, at or just below the national average. The notice points to a 2025 order from Transportation Secretary Sean Duffy directing the department to "give preference to communities with marriage and birth rates higher than the national average." The FTA has said projects that miss that bar "would not otherwise be penalized." The final rules, as proposed, would take effect as soon as they are posted, and "no grandfathering will be allowed for any projects currently in the CIG pipeline."

General Manager Phil Eng, who is also Gov. Maura Healey's interim transportation secretary, signed a five-page comment letter for the T. He wrote that the T has worked with the FTA on the project since May 2022, has already committed more than $1 billion in local money, and was rated favorably in the agency's latest annual report. He warned that the new financial scoring "could result in projects, such as the Green Line Transformation project, falling out of the CIG pipeline despite years of collaborative participation with FTA staff." Because the Green Line runs past several college campuses, he wrote, the corridor has many 18-to-24-year-old residents and "will likely receive no benefit from these bumps." The T asked that the proposal be withdrawn or amended, or that already-rated projects be exempted.

The public comment window closed Monday night last week. The Blue Hill Avenue center-running busway, which received $80.3 million from the same grant program in a spending bill signed in February, is in a smaller-project category, so the marriage-and-birth bonus would not apply to it, though the no-grandfathering rule would, Streetsblog Massachusetts reported. Whether the FTA changes the proposal, and whether the president later puts the Green Line in his budget, remains unanswered.