The T Announced 100 Days of Shutdowns for 2027 and Called It Good News. Here's the Thing: It Kind of Is.
Down from 274 days in 2024. The Green Line still eats 42 of them, and Symphony stays closed into 2029.

The MBTA released its 2027 construction schedule Thursday, and the headline it chose was "significantly fewer planned service outages." The number is 100 days. That's down from 132 this year, 190 in 2025 and 274 in 2024. Most of the work is on weekends.
Before you celebrate, check your line. Mass Daily News counted 42 of those days on the Green Line, 29 on the Red Line including the Mattapan trolley and 17 on the Orange. The central Green Line tunnel shuts between North Station and Babcock Street, Kenmore and Heath Street for signal work, including a nine-day stretch Jan. 16 to 24. Government Center to East Somerville and Union Square goes dark Nov. 13 to 21 for track replacement. Symphony Station stays closed through spring 2029 for four new elevators.
The T says the payoff is new signals on the Red, Orange and Green lines, ready for the new Type 10 Green Line cars, plus radio upgrades and station accessibility work.
My take: an agency announcing 100 days of shutdowns as progress sounds like a joke, but the trend line is real. 274 to 100 in three years is the kind of number riders said they'd never see. The test is whether the trains run better on the other 265 days.
What we still don't know: whether these dates hold, since the T itself says they're subject to change, and how many diversions end up getting added during the year.
Sources
- MBTA: MBTA Announces 2027 Construction Schedule with Significantly Fewer Planned Service Outages (opens in a new tab)
- Mass Daily News: MBTA plans 100 days of subway shutdowns in 2027 (opens in a new tab)
- Boston Globe: T riders should brace for at least 100 days of shutdowns in 2027 (opens in a new tab)

Dez Marlowe is a Boston Uncut reporter covering Boston, Massachusetts, national and world news.